Changing the Schedule

Previous   Top Next

The simplest way to decide how to change the schedule is to ask the question: "Is this a one-time change or an ongoing change?". One-time changes are usually accomplished by working right from the Planner, adding, removing and altering existing Shifts. Ongoing changes to the schedule are generally done on the Times for Service form.

Individual Changes

Here are links to the sections that explain how to make specific, one-time changes to the schedule:

Adjusting Times on a Shift

Adding a Shift

Unassigning Shifts

Splitting Shifts

No Show, Tardy and Did Not Finish

Removing a Shift

Ongoing Changes

Changes to the regular schedule on a Service are done on the Times for Service screen. By adding, removing and editing entries in the Times for Service screen, you can control the ongoing pattern of Shifts needed on a Service, as well as the status of a Service on any particular date.

 

You get to the Times for Service form from the Planner by clicking on the Times button (above the days of the week). On the Service form, the Times button is near the top of the form. In either case, it displays the current Status and/or the Time Pattern that is in effect.

 

times_button_plan

 

times_button_svc

Figure 80: Times Button on the Planner and on the Service form

Once you are in the Times for Service form, you simply Add or modify a pattern to include the Shifts you want.

To see more detail about working with this, see the Times for Service Form section.

 

Conflicts with Existing Shifts

When you change the ongoing schedule, Rosemark will adjust any existing Open Shifts to match the new pattern. However, it will not assume that Assigned Shifts can be automatically adjusted. Therefore, Rosemark checks to see if you already have already assigned Shifts that represent some sort of conflict with the new pattern. If there are any, it will pop up a list of these shifts and present you with a choice: continue with the change or not.

 

change_conflict

Figure 81: Warning that there are conflicting Assigned Shifts

If you decide NOT to continue with the change, everything will remain the way it was before you started to make the change.

If you decide to continue with the change, You will be left with the list of these conflicting Shifts.

 

conflicting_assigned_shifts

Figure 82: List of Conflicting Assigned Shifts

 

On the Planner, you will see the new Open Shifts and you will also see these conflicting Assigned Shifts. Assuming that the Caregiver can work these Shifts, simply remove the Assigned Shifts and assign them to the newly-adjusted Open Shifts. (Note: you could avoid this step by unassigning the Shifts BEFORE adjusting the Time Pattern in the first place).

 

conflicting_assigned_shifts_planner

Figure 83: Planner showing the Conflicting Assigned Shifts